One-time tasks are scripts executed once per environment during deployment, then never again. They are useful for data fixes, initial setup, or one-off migrations that must not re-run on subsequent deployments.

Execution state is stored in the database (one_time_tasks table). A task is only marked complete after it succeeds; if it fails partway through, it will be retried on the next deployment.

One-time task timing

A one-time task can run in two moments:

  • when: before: Before system:update:finish (migrations). Useful when you need data updated before schema changes.
  • when: after: (default) After extensions are managed and installed. This is the safest time for most tasks because extensions are ready.

Example: data migration

yaml
deployment:
  one-time-tasks:
    - id: migrate_old_custom_field_to_new
      when: after
      script: |
        %php.bin% bin/console custom:migrate-field-data

When deployed, this runs once. On the next deployment, DH checks the database and skips it. If you need to run it again, use one-time-task:unmark.

Managing one-time tasks

Check execution history:

bash
./vendor/bin/shopware-deployment-helper one-time-task:list

Returns a table showing which tasks ran, when, and their status.

Mark a task as complete without running it (useful after manual fixes):

bash
./vendor/bin/shopware-deployment-helper one-time-task:mark <id>

Re-run a completed task (removes its completion mark):

bash
./vendor/bin/shopware-deployment-helper one-time-task:unmark <id>

One-time task timeout

By default, a task can run for up to 300 seconds (5 minutes). On large shops with slow queries or batch operations, you may hit this limit. If a task times out, it is marked incomplete and retried on the next deployment.

Increase the timeout via command option:

bash
vendor/bin/shopware-deployment-helper run --timeout=900

Or set the environment variable:

bash
export SHOPWARE_DEPLOYMENT_TIMEOUT=900

Disable timeout entirely (not recommended):

bash
vendor/bin/shopware-deployment-helper run --timeout=null

Best practices for one-time tasks

  • Keep them short. If a task takes > 60s, consider moving it to a post-deploy webhook or scheduled task.
  • Fail loudly. Exit with a non-zero code if something goes wrong, so the deployment fails and the task is retried.
  • Idempotent. Make sure re-running the task is safe. If it's marked done, but you re-run it, it should not corrupt data.
  • Test in staging first. Run the task in a staging deployment before pushing to production.
  • Remove completed tasks. Once a task is done and verified safe, remove it from the config to keep the task list clean for future developers.

One-time task partial failure and rollback

If a one-time task fails partway through, the database may be in a partial state. The task is not marked as complete, so it will retry on the next deployment.

Example: A task that migrates 100k customer records, fails at record 50k:

  • First 50k records are updated (permanent in DB)
  • Task fails
  • Next deployment: retries the task from the beginning

To prevent duplicate updates or corruption, ensure your tasks are idempotent: rerunning them should be safe, even if they partially succeeded before. Use checks like:

bash
# Check if migration already ran before doing work
if ./bin/console custom:check-migration-done; then
  echo "Migration already complete, skipping..."
  exit 0
fi

# Do the migration
./bin/console custom:migrate-data

# Mark it done
./bin/console custom:mark-migration-done

If the task fails halfway, the check in the next run will detect the partial state and either continue or skip safely.